Rang Dong Full Field Development Phase 2 – Offshore Installation Project

Admin 25/08/2025

Tên dự án

RANG DONG FULL FIELD DEVELOPMENT PHASE 2 – OFFSHORE INSTALLATION PROJECT

Phạm vi công việc

Cung cấp Thép kết cấu giàn khoan

Project Description:

– Key Facilities: NCWI and NULQ platform including jackets and topsides and LQ module and 02 bridges, P7 pipeline

– Size: 16” Water Injection Pipeline (P7) – 7.5km

– Weight: NCWI/NULQ decks – 2,500T/ each; NCWI/NULQ jackets – 1,000T/ each; LQ module and helideck – 900T; bridges – 160T/ each

Thời gian thực hiện

2002-2003

Khách hàng

JAPAN VIETNAM PETROLEUM COMPANY (JVPC)

Rang Dong Full Field Development Phase 2 - Offshore Installation Project

Rang Dong Full Field Development Phase 2 – Offshore Installation Project