Lot 2 – Nhon Trach 2 CCPP Project
We received the Transformer and generator directly from the vessel and transport to site by water way. The transformer and generator was finished load in and site move to close with its foundations. Using skid system to skid the transformer sideway onto a temporary storage area; jacked up, down and positioned at the require […]
See moreLoad In And Site Move For Tien Giang Pvpipe Plant
We carried out the following operations: Prepared the barge and temporary supports to receive heavy cargo directly from the vessel onto our barge. Transported the cargo via river from Ho Chi Minh City to PV Pipe Plant in Tiền Giang, unloaded at the dock, and moved the 165-ton machine body to the plant’s equipment storage […]
See moreLoad Out Structure Of Bien Dong 1 Project
We carried out the following operations: Transported and launched the Mộc Tinh topside weighing 3,300 tons onto a barge using hydraulic trailers, along with a ballast water pumping system and mooring winches on September 12, 2011. Transported and launched piles weighing 2,050 tons onto a barge using hydraulic trailers, with a ballast water pumping system […]
See moreLoad Out Hai Thach Jacket, Weight 7.300 Te, VSP Port, Vung Tau
PETROSETCO – ALE successfully launched the Hải Thạch jacket weighing 7,300 tons from the fabrication yard onto a barge using a jacking system, along with a ballast water pumping system and mooring winches, on May 3, 2012.
See moreLot 1 – Nhon Trach 2 Ccpp Project
We received the transformers and generators directly from foreign vessels and transported them via river to the project site. The transformers and generators were launched and moved close to the machine foundation. We then lifted the 320-ton generator from the hydraulic trailer to the required height and moved it 15 meters vertically before placing it […]
See moreLoad Out Of Dai Hung 2 Topsside
PETROSETCO-ALE successfully executed the following scope of work: Transporting and launching the Dai Hung 2 topside, weighing 1,340 tons, from the fabrication yard onto a barge using a specialized hydraulic trailer system, water ballast system, and mooring winch system. The project was completed on May 20, 2011.
See moreLoad Out Of Dai Hung 2 Jacket
PETROSETCO-ALE successfully executed the following scope of work: transporting and launching the Dai Hung 2 jacket, weighing 4,500 tons, from the fabrication yard onto a barge using a skid system, water ballast system, and mooring winch system. The project was successfully completed on April 18, 2011.
See more