Load Out Structure Of Bien Dong 1 Project

Admin 27/08/2025

We carried out the following operations:

  • Transported and launched the Mộc Tinh topside weighing 3,300 tons onto a barge using hydraulic trailers, along with a ballast water pumping system and mooring winches on September 12, 2011.

  • Transported and launched piles weighing 2,050 tons onto a barge using hydraulic trailers, with a ballast water pumping system and mooring winches. Phase 1 was completed on August 31, 2011, and Phase 2 on September 2, 2011.

Load Out Structure Of Bien Dong 1 Project

Load Out Structure Of Bien Dong 1 Project