Load Out Structure Of Bien Dong 1 Project

Admin 27/08/2025

We carried out the following operations:

  • Launched the Mộc Tinh jacket weighing 6,500 tons onto a barge using a sliding system, along with a ballast water pumping system and mooring winches on August 27, 2011.

  • Transported and launched the Mộc Tinh accommodation module weighing 600 tons using hydraulic trailers, with a ballast water pumping system and mooring winches.

 