We carried out the following operations:
-
Launched the Mộc Tinh jacket weighing 6,500 tons onto a barge using a sliding system, along with a ballast water pumping system and mooring winches on August 27, 2011.
-
Transported and launched the Mộc Tinh accommodation module weighing 600 tons using hydraulic trailers, with a ballast water pumping system and mooring winches.

Load Out Structure Of Bien Dong 1 Project