Lot 2 Nhon Trach 2 Ccpp Project

 

We received the Transformer and generator directly from the vessel and transport to site by water way.

The transformer  and generator was finished load in and site move to close with its foundations.

Using skid system to skid the transformer sideway onto a temporary storage area; jacked up, down and positioned at the require location.